Traffic Signal Project This project has installed signals at the intersection of Elder Creek Road and South Watt Avenue and they will provide a number of roadway system benefits:
This project included:
Project Timeline Preliminary Study, 2003 to 2005Environmental Study, 2004 to 2006 Design, 2004 to 2006 Right of Way Acquisition, 2005 to 2006 Construction was completed in November 2006. Funding Estimated total project costs are $1.5 million, and will be provided by Developer Fees (Roadway District 4 funds) and Measure A sales tax funds. Contact Information
Heather Yee, Project Manager |
||
|
|
|||
|
|||