Madison Avenue - Sunrise Boulevard to Hazel Avenue

Project Description

SACDOT concluded a preliminary study for a Madison Avenue (Sunrise to Hazel) improvement project that will provide a number of roadway system benefits including: 

  • Improved roadway safety.
  • Increased traffic capacity to ease congestion and delays.
  • Improved bicycle and pedestrian facilities.
  • Meet Americans with Disability Act requirements.
  • Beautification of the project area.

Planned roadway improvements would include:

  • Widening Madison Avenue from 4 to 6 lanes between Sunrise Avenue and Hazel Avenue in the City of Citrus Heights and the Orangevale area. Project implementation requires a cooperative agreement with the City of Citrus Heights.
  • Construction of a 12-foot wide raised, landscaped median along Madison Avenue.
  • Modifying existing traffic signals, sidewalks, curbs and gutters.
  • Roadway improvements for ADA compliance, transit access and bicycle and pedestrian facilities.

Tentative Schedule

Preliminary Study, 2004 to 2007
Design, 2008 to 2010
Right-of-Way Acquisition, 2009 to 2011
Construction, 2011 to 2012

Funding

Estimated total project costs are $17 million and will be provided by Developer Fees and Measure A Sales Tax.

Contact Information

Steve White, Project Manager
Senior Civil Engineer
916-874-5354
whitest@saccounty.net