Jump to Page Content
www.sacdot.com Where the Commitment to Excellence is Standard Practice Municipal Services Agency, Department of Transportation County of Sacramento
Municipal Services Agency www.sacdot.com Where the Commitment to Excellence is Standard Practice County Home Services Help County Home
  Home   |   Documents   |   Services   |   Projects-Programs   |   About   |   Sitemap     
 
Project Links:

Project Home

Major Roadway Improvement Projects

Vicinity Map

I-5 @ Metro Air Parkway Interchange

Project Description

This State Highway project will construct an interchange at the intersection of Interstate 5 and Metro Air Parkway. This first phase of this project will include:

  • Realignment of South Bayou Way to provide a right-of-way for partial completion of a two-quadrant partial cloverleaf interchange.
  • Construction of a single-lane northbound I-5 exit ramp and diagonal entrance ramp.
  • Construction of a single-lane southbound I-5 exit ramp.
  • Construction of a two-lane southbound I-5 loop entrance ramp with an auxiliary lane.
  • Construction of a three-lane overcrossing and roadway with a connection to the north with Metro Air Parkway and terminating to the south with a cul-de-sac.

Tentative Schedule

Preliminary Engineering 2003 to 2006
Environmental Review 2003 to 2007
Design 2003 to 2007
Right-of-Way Acquisition 2005 to 2007
Construction 2007 to 2009

Funding

Estimated total project costs are $11.28 million. Funding will be provided by the Metro Air Park Financing District (97%) and Measure A sales tax funds (3%).      

Contact Information

Theron Roschen, Project Manager
Chief Engineer
916-874-7225
roschent@saccounty.net