Gerber Road  (Elk Grove-Florin to Gerber Creek Crossing)

Project Description

This project will provide a number of roadway system benefits including:

  • Improving roadway safety.
  • Easing congestion and delays.
  • Improving bicycle, pedestrian and transit facilities.
  • Meeting Americans with Disability Act requirements.
  • Beautification of the project area.

Planned roadway improvements include:

  • Widening Gerber Road from 2 lanes to 3 lanes between Elk Grove/Florin Road and one-quarter mile west of  Bradshaw Road.
  • Construction of a 11-foot wide, raised landscaped median.
  • Improvements for ADA compliance, transit access, bicycle and pedestrian facilities.
  • The project will also include a culvert improvement on Gerber Road at Gerber Creek Crossing #4.

Tentative Schedule

Preliminary Engineering, 2005 to 2007
Design, 2005 to 2007
Environmental Review, 2005 to 2006
Right-of-Way Acquisition, 2006 to 2007
Construction, 1st Phase (North Side), 2006 to 2007
                     2nd Phase (South Side), 2008 to 2009

Funding

Estimated total project costs are $3.33 million and will be financed by the North Vineyard Station Specific Plan Area Fee Account.

Contact Information

Anthony Voo, Project Engineer
Associate Civil Engineer
916-874-7871