This Bradshaw Road (Calvine to Florin) improvement project will provide a number of roadway system benefits including:
- Improved roadway safety.
- Increased traffic capacity to ease congestion and delays.
- Improved bicycle and pedestrian facilities.
- Meet Americans with Disability Act requirements.
- Beautification of the project area.
Planned roadway improvements include:
- Widening Bradshaw Road from 2 to 4 lanes between Calvine Road and Florin Road in the Vineyard area.
- Construction of a 12-foot wide, raised landscaped median along Bradshaw Road.
- Construction of paved shoulders to accommodate bicycle and pedestrian facilities.
- Traffic signal modification at Bradshaw Road @ Gerber Road and traffic signal installation at Bradshaw Road @ Carmencita Avenue and Bradshaw Road @ Knightview Court.
- Replacement of bridges at Laguna Creek and Gerber Creek.
Preliminary Engineering, 2003
Design, 2004 to 2006
Environmental Review, 2005 to 2006
Right-of-Way Acquisition, 2005 to 2006
Construction, 2007 to 2009
Estimated total project costs are $15.4 million and will be provided by Measure A sales tax funds (52%) and Developer Fees: Roadway District 4 (48%).
Crystal Tu, Project Manager