This project will install pedestrian sidewalks and ADA ramps from just west of Rowena Way to just east of Keeny Way. A new drainage system will be installed from just west of Rowena Way to Jonas Avenue.

Project Benefits

This project will: improve safety and accessibility for children and residents to/from the school; improve safety for pedestrians (curb and sidewalks, street lights); improve access for the disabled (sidewalk ramps at intersections).  

Project Schedule

  • Preliminary Design: 2016 to 2017
  • Environmental Review: 2017
    • PERD Control No.:  PLER2017-00002
    • CEQA Review Release to Public: June 16, 2017
    • CEQA Determination: Categorical Exemption
  • Final Design: 2017 to 2019
  • Right-of-Way Acquisition: 2017 to 2018
  • Construction: June 2020 to August 2020

Project Links:

Funding

Estimated construction costs are $644,000, with funding provided by the SACOG 2015 Regional Active Transportation Program (ATP) Cycle 2 with State-only funds and a local percentage match from the Sacramento County Measure A Sales Tax.

Contact Information​

Melissa L. Wright, Senior Civil Engineer
Phone:  916-874-4243
Email: wrightme@saccounty.net

Jenny Singh, Associate Civil Engineer
Phone:  916-874-6092
Email: singhje@saccounty.net